Embedded Generation Connections 5 MW or Greater

 

 

 

Generator connections into the AusNet Services (AST) Distribution Network, are classified as embedded generator connection. The AST distribution network is, generally, defined as all parts of the AST network which operate at 66kV or lower.

This page sets out the process, indicative costs and time frames of embedded generator connections with generation capacity of 5 MW of greater.

Connections into the 220kV (and above) network are considered connections onto the Victorian Transmission Network. The Australian Energy Market Operator (AEMO) manages the connection process for all Victorian Transmission connections and will be your main point of contact. For more information please visit their website.

Need more information?

Email us at energyconnectionsSG@ausnetservices.com.au

 

Time Frames and Process

There are 6 main stages in the process to connect generation capacities of 5 MW or greater to the AST Distribution Network. For a detailed outline of the full connection process please see the Distribution Connection Process Map.

 

The AusNet Services Distribution Network spans the east of Victoria

 

Don't know where to connect? 
Use the Renewable Energy Map to check the available capacity of the our Distribution Network.

 
  • Stage 1. Preliminary Connection Enquiry

    Process

    The first step is for an embedded generator (registered or intending to register with AEMO) to submit a Preliminary Connection Enquiry Form.

    AusNet Services will provide a written acknowledgment via email after receipt of enquiry.

    The connection enquiry will be assessed, and a Preliminary Enquiry Response will be provided. This is a high level response which will include details such as available capacity at the proposed location and AST's assessment of the applicant's ability to connect. 

    This stage is not compulsory and may be bypassed to move directly to the Detailed Enquiry Stage. To do so, a Letter Agreement and a Confidentiality Agreement will need to be executed. See the Letter Agreement Engagement stage below for further details. 

     

    Requirements

    Complete an Embedded Generator Connection Enquiry Form and send it to the Energy Connections Team, energyconnectionsSG@ausnetservices.com.au.

     

    Costs

    No fee for this stage

     

    Time frame

    15 business days for a Preliminary Enquiry Response

     
  • Stage 2. Letter Agreement Engagement

    Process

    To continue the enquiry process a Letter Agreement and Confidentiality Agreement need to be executed. These agreements define the scope of the services AST will provide prior to the execution of the long form Connection Agreements. 

    Costs payable under the Letter Agreement are associated with works undertaken by AST for the following stages:


    1. Connection Application
    2. Offer preparation; and
    3. Contract negotiations.

    An upfront non-refundable Advance Payment is payable upon Letter and Confidentiality Agreement execution. This Advance Payment does not constitute the total consideration payable to AST by a Connection Applicant.

    Due to the iterative nature of the detailed enquiry and connection application stages an overall sum payable by the Connection Applicant cannot be determined in the early stages of a project and billing will be on an hourly basis after the initial Advance Payment has been exhausted.

    If a Preliminary Enquiry Response has been provided by AST, the response will include a dedicated Point of Contact for that project. To execute the Letter and Confidentiality Agreements please send an email to the project's Point of Contact requesting to commence the Letter Agreement Engagement stage. The Point of Contact will then provide draft copies of these agreements for the Connection Applicant's review and execution.

    If the Preliminary Enquiry stage was bypassed and the Connection Applicant has chosen to move directly to Detailed Enquiry stage, there will be no assigned Point of Contact. Please send an email to energyconnectionsSG@ausnetservices.com.au requesting a copy of both the Letter and Confidentiality Agreements.

     

    Requirements

    1. Send an email to your Point of Contact requesting to commence the Letter Engagement Agreement stage.
    or
    2. Send an email to energyconnectionsSG@ausnetservices.com.au requesting to commence the Letter Agreement Engagement stage.

     

    .

     

     

    Costs

    An initial non-refundable Advance Payment of $20,000 (excl. GST) payable at execution of Letter and Confidentiality Agreements. 

    Fees are charged at an hourly rate each month as they are incurred and are initially offset against the Advance Payment. 

     

     

     

    Time frame

    Time frame is variable and dependant on contract negotiations.

     
  • Stage 3. Detailed Enquiry

    Process

    The Detailed Enquiry Response provides a high level scope and cost estimate for the project along with a draft copy of AST's connection agreement. 

    After the Letter and Confidentiality Agreements have been signed, the Connection Applicant may lodge a Detailed Enquiry Form to the Point of Contact. 

    The Connection Applicant must submit a completed form along with all additional information requested by AST. AST will then confirm receipt of all information via email and a Detailed Enquiry Response will be provided within 30 Business Days.

     

    Requirements

    1. Lodge the Detailed Enquiry Form to the Point of Contact.
     

    Costs

    No additional fees will be charged. 

    The Detailed Enquiry stage costs are charged under the Letter Agreement. 

     

    Time frame

    Once all information required on the Detailed Enquiry Form is received and confirmed, AST will provide a Detailed Enquiry Response within 30 Business Days.  

    Overall time frame for this stage can vary between 3 – 6 months. These time frames are estimates only.  

     

     

  • Stage 4. Connection Application

    Process

    The Connection Applicant may proceed to the Connection Application stage following consideration of the Detailed Enquiry Response. 

    To commence this stage a Connection Application Form must be submitted. 

    There are a few inputs needed in order to commence assessing the connection application.  The connection application will not be deemed complete until all required criteria is met as required by the Connection Application Form

    Once AST has received all of the required information outlined in the form, preparation of a firm offer to connect will commence. During the Connection Application process AST will consult with AEMO and, if required, existing customers at the Applicants proposed point of connection.  

     

    Requirements

    1. Lodge the Connection Application Form with the Point of Contact along with all information requested as part of that form.  
     

    Costs

    No additional fees will be charged. 

    The Connection Application stage costs are charged under the Letter Agreement. 

    AEMO’s costs to review the network study and GPS will be passed through to the applicant per the terms of the Letter Agreement.  

     

    Time frame

    The time frame for this stage is dependent on the information provided from the applicant. Assessing the Connection Application is usually an iterative process. 

    Typically, this stage takes 6-9 months. These time frames are estimates only.

  • Stage 5. Offer and Contract Execution

    Process

    Once AST has confirmed receipt of a complete Connection Application, a Firm Offer will be provided within 4 months. The Firm Offer sets out the costs AST will charge to complete all works required to connect the embedded generator to the distribution network.  

    The Applicant has 20 Business Days to accept the offer once provided by AST.

    After the Firm Offer is accepted, the parties then negotiate long form Connection Agreements.  The Connection Agreements govern the ongoing connection services to be provided by AST, as well as the network augmentation/extension works which are required. 

    Certain parts of the network augmentation/extension work may be undertaken by AST or the applicant, depending on the nature of the work to be undertaken.

    Upon execution of the Connection Agreements delivery of the project will commence.

     

    Requirements

    1. A Complete Connection Application.
    2. Acceptance of the Firm Offer by the Applicant.
     

    Costs

    No additional fees will be charged. 

    The Offer (including negotiations) and Contract Execution stages costs are charged under the Letter Agreement.  

     

    Time frame

    Typically, this stage takes 6-12 months depending on contract negotiations. These time frames are estimates only. 

     

     

     
  • Stage 6. Project Delivery

    Process

    The Project Delivery stage will commence once conditions precedent in the Connection Agreements have been met and payment has been made by the Applicant. 

    While the Network Augmentation / Extension works are progressing, the Applicant can commence construction of the Generating Plant in parallel. 

    The Applicant will not be able to generate until AusNet Services has achieved Practical Completion and energised the assets up to the agreed Point Of Connection. 

    Once energised, the Applicant can commence commissioning of the Generating Plant. AST will assist the Applicant to ensure the plant has been commissioned in accordance with the Commissioning Plan and all Generator Performance Standards (GPS) requirements have been met. 

    AST will provide the Applicant with a GPS Compliance Letter to mark the completion and satisfactory compliance of the Generating Plant. This concludes the connection process.

     
    Requirements

    1. Execute Connection Agreements
    2. Meet Conditions Precedent
    3. Make payment per Connection Agreements.
     


    Costs

    Project connection costs per Connection Agreements.

     


    Time frame

    Project Delivery is highly dependent on project scope.

     

     

     
     

Previous Connections

For a list of previously connected embedded generation projects, please download our Register of Completed Embedded Generation Projects. This list is published with our existing customers’ consent.